A new 350 student elementary school for Quispamsis was announced in the 2012-2013 provincial budget.

  • Fall 2012
    • Department of Transportation and Infrastructure determined there is space to construct a two level 350 student K-5 school. The location was approved by the District Education Council (September 2012)
    • Educational Specifications document developed – led by Josh Nowlan, Senior Project Manager, Department of Education & Early Childhood Development.  This document is unique to each school project and outlines the size and use of the spaces in the school
    • Meetings with the Town of Quispamsis to look at growth, trends in housing starts.
    • Examination of enrolment trends and kindergarten registrations for 2012-13
  • Winter 2012
    • Educational specifications signed off by committee and approved by District Education Council and forwarded to Minister
    • Minister of Education Jody Carr & MLAs visited the site January 2013 and a sign was erected
  • Spring 2013
    • Adjacency drawings developed by the committee and Josh Nowlan
    • Transportation staff began to examine boundaries
  • Fall 2013
    • Two meetings to review and give feedback on the architect’s schematic drawings
    • Initial meeting with Principals and Transportation to examine boundaries
  • Spring 2014
    • Architect and Contractor named

The new school will have the following features:

  • 4 kindergarten classrooms
  • 14 classrooms
  • 5 resource/special care areas
  • Student project areas
  • Music room
  • Performing arts class
  • Double gym/change rooms
  • 4 kindergarten classrooms
  • 14 classrooms
  • 5 resource/special care areas
  • Student project areas
  • Music room
  • Performing arts class
  • Double gym/change rooms

Next Steps:

  • May 2014
    • Parent Open House for Quispamsis Middle and individual meetings for the elementary schools
  • Fall 2014
    • Boundaries finalized after parent meetings
    • Naming of the new school – committee will be formed (DEC member, District Staff person, Dept. Staff person, a community rep named by the DEC)
    • QMS Field ready for September 2014
  • Winter 2015
    • New Principal hired January 2015
  • Fall 2015
    • New school open September 2015